Transmission Network Review in Pakistan
British Power International was appointed to work alongside the National
Transmission and Despatch Company (NTDC) of Pakistan to identify the
existing constraints of the transmission system, develop suitable network
projects to remove those constraints and provide capacity for the projected
demand. This included a technical, financial and economic evaluation of the
projects, and importantly an assessment of the environmental and social
impacts that each project would bring.
The 500kV and 220kV network in Pakistan has been under severe stress for
many years. The transmission lines and the transformers have been running
over and above their installed capacities, with little or no margin in their
capacities to withstand any disturbances. BPI’s delivery of this project
helped to finance the enhancement of the transmission capacity of the 500kV
and 220kV network, which is the back-bone of the entire National Grid of
Pakistan. Nineteen sub-projects were prepared for Phase 1 of the overall
project, after BPI demonstrated that they fulfilled the technical, economic,
financial, environmental and resettlement criteria to be fully eligible for
approval by the Asian Development Bank (ADB), who were providing funds for
the project.
Full technical studies, including load flow analysis and, where appropriate,
short circuit level and transient stability analysis, were carried out to
support each identified subproject. The technical studies confirmed that for
each sub-project the proposals were technically valid and beneficial to the
national transmission system. A technical feasibility summary of each
sub-project was prepared along with environmental and resettlement plans as
appropriate for approval by ADB. The technical analysis we carried out
determined the scope of work of the sub-projects, detailed cost estimates
and evaluated MW benefits to convert to financial benefits.
In view of the later than expected award of the contract, ADB asked us to
deliver the project as a fast-track assignment, reducing the elapsed time of
the project plan to meet the timescale agreed between the Government of
Pakistan (GoP) and the Bank for processing this loan and enabling funded
projects to start. This fast-track delivery required some rearrangement of
the commitments of our team and a reschedule of work, so that some work was
delivered out of country. This was achieved through flexibility on behalf of
BPI, often working to very tight timescales.
Throughout the project we adopted a method of working which maximised the
participation of counterpart staff and others with an interest in NTDC.
Weekly briefing notes were prepared and weekly review meetings were held
with NTDC to discuss progress, resulting in a free and informal exchange of
information. This approach made it possible to meet tight deadlines and
culminated in approval of project funding from the ADB, within the required
timescales. A high level plan for the project was prepared, presented in the
Inception Report and used as the prime project management document, ensuring
that the interrelationships and target dates for outputs were met.
Whenever possible we involved NTDC staff in our work, for example when
performing technical system studies to support identified sub-projects. As a
result, local planning staff have achieved high levels of competence in
performing system studies on transmission and distribution networks.
* Please note that we maintain commercial confidentiality regarding work undertaken for customers. While we will be happy to deal with any questions about these case studies, please understand that there may be strict limits to what further information will be disclosed.
Case Studies
- Transmission Design in the Netherlands
- Transmission Network Review in Pakistan
- Distribution Network Planning in China
- Innovative substation design in the UK
- Business planning and change in Nigeria
- Removing Hydropower Barriers in Nepal